Definition:
To-Complete Performance Index with Revised Estimate (TCPIRE) represents the efficiency required to achieve the revised estimate at completion. It measures the ratio of the remaining work value to the remaining budget based on a revised estimate. TCPIRE helps in evaluating the project's cost performance against the revised estimate and assessing the efficiency needed to complete the project within budget.
Calculation: TCPIRE = (BAC - EV) / (EACRE - AC)
Make sure you never miss out! Sign up to our monthly newsletter to keep up with the biggest news stories in construction and the latest Raildiary updates. Full of our latest case studies, blogs and fun quizzes!
Rail Diary needs the contact information you provide to us to contact you about our products and services. You may unsubscribe from these communications at anytime. For information on how to unsubscribe, as well as our privacy practices and commitment to protecting your privacy, check out our Privacy Policy.