To-Complete Performance Index with Schedule Performance (TCPI-S)

What is To-Complete Performance Index with Schedule Performance (TCPI-S)? Earned Value Management explained.

Definition: 

To-Complete Performance Index with Schedule Performance (TCPI-S) represents the efficiency required to achieve the project objectives based on schedule performance analysis. It measures the ratio of the remaining work value to the remaining budget, considering the schedule performance indicators. TCPI-S helps in assessing the efficiency needed to meet the project objectives using schedule-based indicators.

Calculation: TCPI-S = (BAC - EV) / (BAC - AC)

Keep up with Raildiary

Make sure you never miss out! Sign up to our monthly newsletter to keep up with the biggest news stories in construction and the latest Raildiary updates. Full of our latest case studies, blogs and fun quizzes!

Thank you for subscribing!
Oops! Something went wrong while submitting the form.

Rail Diary needs the contact information you provide to us to contact you about our products and services. You may unsubscribe from these communications at anytime. For information on how to unsubscribe, as well as our privacy practices and commitment to protecting your privacy, check out our Privacy Policy.